A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM MOST likely perform?
A.
Call the previous PM for advice on risks and issues.
B.
Ask the project sponsor to provide previous final project report results.
C.
Complete the project charter using the other PM's subject matter expertise.
D.
Use existing artifacts and accommodate based on the current project success criteria.
This one is pretty straight forward and I’m going to say D
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
jksdbfb
11 months, 2 weeks ago