A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take NEXT?

  • A. Assign more resources to complete similar stories in the future.
  • B. Break the stories into workable items that can be completed within one sprint.
  • C. Extend the sprint duration when required with the approval of the product owner.
  • D. Release the current progress into production and carry over the rest of the code for the next sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jksdbfb
11 months, 2 weeks ago
Selected Answer: B
B - In this scenario, since the developer focused on a single story for the entire sprint and it wasn't completed due to underestimation, the Scrum team should consider breaking stories into smaller, more manageable items that can be completed within one sprint. This practice helps ensure that work is sized appropriately and can be completed within the sprint's time frame. It's important to maintain a sustainable pace and aim for regular delivery of increments to increase predictability and value delivery.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...