exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 74 discussion

Actual exam question from CompTIA's PK0-005
Question #: 74
Topic #: 1
[All PK0-005 Questions]

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

  • A. Decline because it is not included in the project scope.
  • B. Assess the impact of the request and create a change request.
  • C. Create new functional and non-functional requirements for mobile devices.
  • D. Revise the baseline of the project plan by adding the new requirements.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
2f0b60f
9 months ago
Selected Answer: B
Assess the impact of the request and create a change request: This is the best practice in project management. Before making any changes to the project, it's crucial to understand their potential impact on time, cost, and resources. A formal change request would go through a change control board or equivalent governance structure, where the decision to approve or reject the change would be made.
upvoted 1 times
...
jksdbfb
9 months, 1 week ago
Selected Answer: B
B ID correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...