Actual exam question from CompTIA's PK0-005
Question #: 70
Topic #: 1
[All PK0-005 Questions]

For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

  • A. Resource plan
  • B. Organizational chart
  • C. Project charter
  • D. RACI chart
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
2f0b60f
9 months, 3 weeks ago
Selected Answer: D
For illustrating roles for major project activities, a "D. RACI chart" would be the MOST useful option. A RACI chart stands for Responsible, Accountable, Consulted, and Informed. It is a matrix designed to assign and display responsibilities for every task, milestone, or key decision involved in completing a project. It helps in clarifying roles and responsibilities in cross-functional or departmental projects and processes.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...