Question #: 101
Topic #: 1
[All PK0-005 Questions]

During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?

  • A. Create a change request for the change advisory board.
  • B. Work with the business analyst to document the new epic.
  • C. Reject the change to prevent scope creep.
  • D. Update the risk register and the work in the mitigation plan.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
1324c82
3 months, 1 week ago
Selected Answer: B
It's coming from the Product Owner, no need for a change request.
upvoted 1 times
...
Jay_Bee14
5 months, 3 weeks ago
Selected Answer: B
If someone in the organization wants a change in the Product Backlog, they need to discuss this with the Product Owner and try to convince them. But at the end of the day, the Product Owner makes the decision.
upvoted 2 times
...
JBD
7 months, 3 weeks ago
Selected Answer: B
Its coming from the Project Owner, what he says goes. Hes in charge of making the changes. This would be B.
upvoted 1 times
...
2f0b60f
7 months, 3 weeks ago
Selected Answer: A
The answer is A. Create a change request for the change advisory board. The Scrum master is responsible for facilitating the Scrum process and ensuring that the team follows the Scrum guidelines. This includes preventing scope creep, which is the uncontrolled growth of the project scope. When the product owner asks to add new scope to the backlog, the Scrum master should first create a change request. This will document the change and allow the team to assess its impact on the project. The change request will then be submitted to the change advisory board, which is responsible for approving or rejecting changes to the project. Option B, working with the business analyst to document the new epic, is not the best course of action because it does not address the issue of scope creep. The Scrum master should first create a change request to document the change and allow the team to assess its impact.
upvoted 3 times
JBD
7 months, 3 weeks ago
Its coming from the Project Owner, what he says goes. Hes in charge of making the changes. This would be B.
upvoted 1 times
Realiable_0
5 months, 3 weeks ago
Key word here is "new scope to the BACKLOG" meaning he has the authority to add/prioritize what is in the backlog for agile environment. So yes IT would be B since it is coming from the product owner.
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago