Question #: 338
Topic #: 1
[All 220-1102 Questions]

A department manager submits a help desk ticket to request the migration of a printer's port utilization from USB to Ethernet so multiple users can access the printer. This will be a new network printer, thus a new IP address allocation is required. Which of the following should happen immediately before network use is authorized?

  • A. Document the date and time of the change.
  • B. Submit a change request form.
  • C. Determine the risk level of this change.
  • D. Request an unused IP address.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TacosInMyBelly
Highly Voted 1 year, 6 months ago
Selected Answer: C
Order of change management phases: 1. Request forms 2. Purpose of change 3. Scope of the change 4. Date and Time of the change 5. Affective systems/ impact 6. Risk analysis 7. Change board approval 8. Finally end user acceptance. You would do #6 before #7. This question says "immediately" stating what is the step to be taken RIGHT BEFORE it is allowed on the network (approved). I'm going with Risk analysis - C.
upvoted 8 times
yutface
1 year, 2 months ago
I tend to agree - however - shouldn't you technically do #4 first? It comes before #6 and wasn't mentioned that it has been done yet. Sounds like CompTIA trying to "get" us.
upvoted 1 times
yutface
1 year, 1 month ago
On further review - a change request form has not been filed yet. That is step 1.
upvoted 2 times
...
...
...
032e128
Most Recent 5 months, 2 weeks ago
Selected Answer: C
I meant c
upvoted 1 times
...
032e128
5 months, 2 weeks ago
Selected Answer: D
Risk comes before request
upvoted 1 times
...
dickchappy
7 months, 1 week ago
Selected Answer: C
I believe the key word here is "immediately before network use is authorized" This implies we are at the end of the change management process, which should involve risk analysis and then approval.
upvoted 1 times
...
faisal83
7 months, 3 weeks ago
Why not B ? Please explain
upvoted 1 times
...
Sanan4ik
1 year ago
Selected Answer: D
Other options may be applicable as part of the network change process, but they are not the first steps before allowing a new printer to use the network.
upvoted 2 times
...
Mamad66
1 year, 1 month ago
Selected Answer: D
D is correct.
upvoted 1 times
...
CookieChip
1 year, 7 months ago
Selected Answer: C
Check risk first, then change request.
upvoted 2 times
...
rknard22
1 year, 7 months ago
Selected Answer: B
change request first before anything else
upvoted 3 times
...
Paula77
1 year, 7 months ago
Selected Answer: C
The logical step is to understand the risks associated with the change, what precautions need to be taken and what steps are necessary to mitigate risk.
upvoted 3 times
...
Perpendicular
1 year, 7 months ago
The change request form should have all the info needed for the board to make an approval no? So you determine the risk level before you submit the request as the risks should be in the request form. Or do you submit the request and after approval you do the assesment? Doesn't sound logical. I will go for C here.
upvoted 2 times
...
TonxhiPatonxhi
1 year, 7 months ago
Selected Answer: B
Change request
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago