Exam PK0-005 topic 1 question 88 discussion

Actual exam question from CompTIA's PK0-005
Question #: 88
Topic #: 1
[All PK0-005 Questions]

A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?

  • A. Continue to monitor the system performance.
  • B. Resize the resource utilization to reflect current needs.
  • C. Reinforce adoption over time.
  • D. Raise an item in the issue log.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
gorilla2001
6 months, 3 weeks ago
Selected Answer: B
it's NOT D because there is no issue. Yes, the usage in only at 20%, but that's not an issue. Also, the PM wouldn't be resizing the resources, they would tell someone else to do it.
upvoted 1 times
...
throughthefray
1 year ago
Wow... there's just straight up not enough information in this question to answer it with any measure of confidence. Is it an IAAS system that MUST be used by the employees to its full capacity? If "No", then its B. If "yes" then it's D.
upvoted 1 times
...
DWtriple0
1 year ago
This Question does not provide enough context for an answer. If i get this question I'll skip it in protest.
upvoted 3 times
...
AdmiralGimme
1 year, 1 month ago
Why not A? Just because it is currently at 20% can't it go up at a different time? Also, B would not be the PM but they would have some sys admin do it.
upvoted 1 times
...
mrdavy
1 year, 4 months ago
Selected Answer: B
I would lean to D since it make sense from a IT perspective, but B) Resize the resource only if SLA allows and then you can negotiate with the vendor. In a perfect Project+ situation, that would be feasible to rescale your resources.
upvoted 2 times
DiverOfSkies
1 year, 2 months ago
from an IT perspective would be to resize the resource utilization so you would select B not D, and from a PM perspective would be to create an event in the issue log so D. also there is no mention of a SLA so in your speculation, answer B would only feasible if the SLA allows this.
upvoted 1 times
...
...
b0ad9e1
1 year, 4 months ago
Selected Answer: D
I think the answer is Raise an item in the issue log. Why would a PM resize the resource utilization? He is not a systems administrator. he is PM.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.