exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 1 discussion

Actual exam question from CompTIA's PK0-004
Question #: 1
Topic #: 1
[All PK0-004 Questions]

A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?

  • A. Network diagram
  • B. Ishikawa diagram
  • C. WBS
  • D. Gantt chart
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jerry47
Highly Voted 5 years, 2 months ago
Wouldn't "D. Gantt chart" be better?
upvoted 11 times
...
FaultlessR
Highly Voted 5 years, 2 months ago
I'm more inclined to agree with the provided answer. A Gnatt chart is basically a representation of a schedule that has already been established. The question is asking which should be used to establish a sequence. Gnatt chart is basically just a glorified calendar of events we already know the sequence of. Someone please correct me if I'm wrong.
upvoted 5 times
...
cepojo
Most Recent 2 years, 3 months ago
A. Network Diagram Gantt Charts already have the time defined. They show the relation of different tasks to each other. Their task dependencies, slack time, and so on.
upvoted 1 times
...
Anthony053
3 years, 2 months ago
A. Network Diagram: used to illustrate the sequence and dependencies for activities in a project.
upvoted 2 times
...
st14
3 years, 3 months ago
The keyword is "establish", therefore Network Diagram is correct. Gnatt Chart shows items in order with duration, it isn't used to establish the duration of project activities.
upvoted 1 times
...
4007
3 years, 10 months ago
D. Gantt chart - The Gantt charts shows both sequence AND duration. Network charts show only sequence.
upvoted 3 times
...
Tom_123
4 years ago
A network diagram can be created to schematically show the sequencing of projects. Keyword in the question is sequencing. Therefore, the answer is A.
upvoted 3 times
...
uRT0228
4 years, 2 months ago
The keywords in this question are "sequence" and "duration". This makes "Network Diagram" much more appealing based on the Study Guide. "One technique used by PM to sequence activities is a network diagram. A network diagram depicts the project activities and interrelationship amount these activities....A commonly used network diagramming method is precedence diagramming method (PDM).....Simple PDM network diagram of tasks with finish to start dependencies and task durations." Source: Page 99 - CompTIA Project+ (PK0-004) Study Guide 2nd Edition. ISBN 978-1-119-28052-1
upvoted 2 times
...
Raddy_PM
4 years, 2 months ago
the answer is network diagram or gnatt chart?
upvoted 1 times
...
sasquatchshrimp
4 years, 3 months ago
I think I may need to agree that a gnatt chart is "MOST" beneficial as the question asks. A gnatt chart is far more clear than a network diagram. It offers dates where as a network diagram does not. A Gnatt chart has more to offer, a network diagram has less to offer. https://analysistabs.com/gantt-chart/vs-network-diagram/
upvoted 1 times
...
[Removed]
4 years, 7 months ago
A network diagram depicts the project activities and the interrelationships among these activities. Gantt charts - can show milestones, deliverables, and all the activities of the project including their durations, start and end dates, and the resources assigned to the task. (Comptia Project+ study guide, 2nd ed.)
upvoted 2 times
...
FaultlessR
5 years, 2 months ago
Revisiting this. I think jerry47 might be correct. A Gantt chart is actually a type of network diagram along with the PERT diagram.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago