Question #: 33
Topic #: 1
[All PK0-005 Questions]

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

  • A. Responsibility assignment matrix
  • B. Acceptable communication channels
  • C. Risk registry
  • D. Staff directory
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheFai
7 months, 3 weeks ago
Selected Answer: B
Acceptable communications channels isn't an actual document named in any of my Project+ books, but a RACI matrix doesn't fit. Risk Registry doesn't fit. Staff directory would have his contact information on it, but it wouldn't indicate he prefers to be called. If anything this would belong on a Communication Plan but that isn't an option.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago