Exam PK0-005 topic 1 question 54 discussion

Actual exam question from CompTIA's PK0-005
Question #: 54
Topic #: 1
[All PK0-005 Questions]

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

Purpose -

Scope of work -

Location of work -

Period of performance -

Deliverables schedule -

Applicable standards -

Acceptance criteria -

Special requirements -

Payment schedule -
Which of the following documents did the client provide to the project manager?

  • A. RFP
  • B. WBS
  • C. SLA
  • D. SOW
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AdmiralGimme
7 months, 2 weeks ago
Selected Answer: D
SOW has all these things in it.
upvoted 1 times
...
TheFai
7 months, 2 weeks ago
Selected Answer: D
Feels like the SOW.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.