A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
A.
A project manager assigned the wrong resources.
B.
A project manager did not release the resources.
C.
A project manager did not remove the system access.
D.
A project manager did not provide the project sign-off.
The allocation refers to being assigned to a project. One PM didn't release them from their project, while the 2nd PM assigned them to their project.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TheFai
7 months, 2 weeks ago