Question #: 56
Topic #: 1
[All PK0-005 Questions]

A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

  • A. A project manager assigned the wrong resources.
  • B. A project manager did not release the resources.
  • C. A project manager did not remove the system access.
  • D. A project manager did not provide the project sign-off.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheFai
7 months, 2 weeks ago
Selected Answer: B
The allocation refers to being assigned to a project. One PM didn't release them from their project, while the 2nd PM assigned them to their project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago