A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
Return on Investment is the only applicable answer. SOW is the Statement of Work. Request For Information / Request for Proposal are for bidding.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TheFai
10 months, 1 week ago