Actual exam question from CompTIA's PK0-005
Question #: 163
Topic #: 1
[All PK0-005 Questions]

Given the following velocity chart:



Which of the following updates on the project status should the Scrum master provide to the senior management team?

  • A. The project utilized all of its available reserve.
  • B. The project has scope creep.
  • C. The project deviated from the critical path.
  • D. The project is trending ahead of schedule.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ducko
10 months, 2 weeks ago
The only justification I can give for 'A' is that on day 8 and 9, the project was behind schedule and was trending that way. You could then assume that the PM utilized the reserve to reverse that trend. 'D' is correct for sure, the question is which one is 'more' correct.
upvoted 1 times
...
BlueMan93
11 months, 3 weeks ago
Selected Answer: D
This chart is showing they completed (let's say) 10 tasks in (let's say) 16 days when they projected it would take 21 days to complete 10 tasks.
upvoted 3 times
...
Therealjosh
1 year ago
Selected Answer: D
A velocity chart is a tool used in agile project management to track the progress and performance of a project team over time. It shows the number of features or user stories completed in each iteration or sprint. The planned timeline line represents the expected or ideal velocity, while the actual effort line shows the actual or achieved velocity. By comparing the two lines, the Scrum master can identify any gaps, trends, or issues in the project delivery. Based on the image, the most likely update that the Scrum master can provide to the senior management team isD. The project is trending ahead of schedule. This is because the actual effort line is above the planned timeline line for most of the time, indicating that the project team is completing more features than expected in each sprint. This means that the project is ahead of schedule and has a positive velocity variance
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...