Several stakeholders have declined the invitation for the kickoff of a major digital transformation project. Which of the following actions should the project manager take NEXT?
A.
Escalate directly to the project sponsor.
B.
Push the kickoff meeting out by one week.
C.
Proceed with the kickoff as planned.
D.
Identify replacements for project stakeholders.
If the question specified the importance of the stakeholders being present I would say A. But since the question doesn’t specify importance of them attending Ill default to C.
The project sponsor is the person who provides the authority, funding, and support for the project. The project sponsor can also help to influence and engage the key stakeholders who are essential for the success of the project. If several stakeholders have declined the invitation for the kickoff meeting, which is an important event to establish the vision, scope, and expectations of the project, the project manager should escalate this issue to the project sponsor and seek their assistance to ensure the participation of the stakeholders
Per AI source...
C. Proceed with the kickoff as planned: It is important to maintain the project schedule and proceed with the kickoff meeting as planned to avoid delays. The project manager can then schedule separate sessions with the stakeholders who were unable to attend to cover the key points and ensure they are aligned with the project’s objectives and plan.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
95d3b92
2 months, 2 weeks agoSkydragon208
5 months agoducko
9 months, 2 weeks agoeXhilarat3d
11 months ago