In a project with a ׀’׀׀¡ of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
A.
The project is under budget and ahead of schedule.
B.
The project is over budget and ahead of schedule.
C.
The project is under budget and behind schedule.
D.
The project is over budget and behind schedule.
The answer indicated is A but this is incorrect. The question states that the CPI is 0.80 which is less than 1.0 and that indicates that it's 'over budget'. The SPI is 1.20 which is greater than 1.0 which indicates that it's 'ahead of schedule'. The correct answer is B.
For Indexes, BELOW 1.0 results are BAD.
CPI less than 1.0 = over budget......BAD
CPI more than 1.0 = under budget......GOOD
SPI less than 1.0 = behind schedule......BAD
SPI more than 1.0 = ahead of schedule.......GOOD
CORRECT ANSWER: B
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Steele08
Highly Voted 5 years, 5 months agoHavok
Highly Voted 5 years, 3 months agoJohnWH
Most Recent 4 years agoAyoyemi
5 years, 1 month ago