In a project with a ׀’׀׀¡ of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

  • A. The project is under budget and ahead of schedule.
  • B. The project is over budget and ahead of schedule.
  • C. The project is under budget and behind schedule.
  • D. The project is over budget and behind schedule.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Steele08
Highly Voted 5 years, 5 months ago
The answer indicated is A but this is incorrect. The question states that the CPI is 0.80 which is less than 1.0 and that indicates that it's 'over budget'. The SPI is 1.20 which is greater than 1.0 which indicates that it's 'ahead of schedule'. The correct answer is B.
upvoted 22 times
...
Havok
Highly Voted 5 years, 3 months ago
this is ahead of schedule but over budget. B
upvoted 14 times
...
JohnWH
Most Recent 4 years ago
For Indexes, BELOW 1.0 results are BAD. CPI less than 1.0 = over budget......BAD CPI more than 1.0 = under budget......GOOD SPI less than 1.0 = behind schedule......BAD SPI more than 1.0 = ahead of schedule.......GOOD CORRECT ANSWER: B
upvoted 2 times
...
Ayoyemi
5 years, 1 month ago
B. Correct answer
upvoted 12 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...