A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

  • A. Status report
  • B. Organizational chart
  • C. RACI matrix
  • D. Meeting minutes
  • E. Communication plan
Show Suggested Answer Hide Answer
Suggested Answer: AD 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Manson_Ng
Highly Voted 4 years, 3 months ago
A and E is the right answer
upvoted 12 times
...
Ayoyemi
Highly Voted 4 years, 10 months ago
A and D is the right answer
upvoted 7 times
...
cepojo
Most Recent 2 years, 3 months ago
Selected Answer: AE
Incorrect answer key: Correct answer is A & E A. What is the current status E. How does the stakeholder want to be contacted. (Communication plan)
upvoted 1 times
...
brown705
2 years, 9 months ago
I thought A and E as well
upvoted 2 times
...
catastrophie
3 years ago
This should be: A. Status Report (This is what the stakeholder is unaware of) E. Communications Plan (The PM must consult this document to decide which type of communication the stakeholder prefers. Does the SH want an email? Do they prefer phone call?) Why not D? What meeting minutes are you going to provide them with? The entire projects worth of meeting minutes? Since the last update? I can tell you for one that I would not want to sift through your meeting minutes looking for tidbits of update information here and there. Thats the PM job to put that all together and provide to me. Keep it to what I need to know right now to get me up today on the status.
upvoted 4 times
...
Jjohnbrown1334
3 years, 4 months ago
A and E definitely seems to be the right answer
upvoted 2 times
...
Jakesn
3 years, 8 months ago
A and D are the correct answers
upvoted 3 times
...
SamEsther
3 years, 11 months ago
A and D are correct. Status report and meeting agenda will help him know about project progress. Status report is a report to stakeholders on the status of the project deliverables, schedule, risks, issues, and more. Meeting minutes describe what was discussed and the decisions made at the meeting.
upvoted 2 times
...
valdw007
4 years, 1 month ago
A and E make more sense, since they have information on the status (A) and which Stakeholders are informed (E) about the project. It is true that RACI is generally used to provide clarity on the roles and responsibilities assigned to each project team member, but these members are not necessarily informed. The reason why I go for A and E.
upvoted 2 times
...
sasquatchshrimp
4 years, 3 months ago
I would agree with @Manson_Ng. A is used to inform the stakeholders, and E is used to know who "all" stakeholders are and who it should be communicated too and how.
upvoted 3 times
...
Steele08
5 years, 2 months ago
I think the answer provided would indicate what you'd need if you were going to inform a single stakeholder as the question seems to indicate in the first statement. However the question asks which documents should the project manager consult to "ensure all stakeholders are notified of project changes". This changes the context to stakeholders in general. With that being said the correct answers would be C and E. The RACI Matrix and the Communication Plan. Remember, RACI stands for Respsonsible, Accountable, Consulted and Informed. The Communication Plan would specify who should be informed as well.
upvoted 5 times
abhnn
4 years, 6 months ago
I agree with this, status report and meeting minutes makes no sense
upvoted 1 times
...
joe_smoe
4 years, 4 months ago
RACI says nothing about stakeholders, status report does Project status reporting is a regular, formalized report on project progress against the project plan. ... It keeps project stakeholders informed of critical aspects of project health such as schedule, issues, scope, resources, cost, etc and allows management to take action to address project issues and risks
upvoted 2 times
dyers
3 years, 8 months ago
but stakeholders covers almost anyone involved with the project, if the stakeholder in question is a team member, than the RACI will tell if he needs to be informed on a specific item or not.
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago