This one is either tricky or is missing the "All of the above" options. Every one of these is a characteristic of the project and none jump out as the 'best' answer.
I think C is the only one that fits correctly.
A. It solves a business problem. services can solve a business process and is not part of a project
B. It created a unique service. several services can be unique and not be part of a project
C. It has a definite beginning and end. projects have a beginning and end and include A,B, C, D.
D. It adheres to a formal framework. several business practices fall into a formal framework and not part of a project.
I think it is missing the "All of the above". But if it is "which is Not" then the answer is D. Other than that it is between A and C because not all projects create services. Some only create a product.
Haha, that would make a lot of sense. If it is "NOT" the answer should be D
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Steele08
Highly Voted 5 years, 2 months agosasquatchshrimp
Highly Voted 4 years, 3 months agoDunboy
Most Recent 2 years, 2 months ago[Removed]
2 years, 10 months agoWes_60
3 years, 7 months agoace012k8
4 years, 1 month agol0609890
4 years ago