This chart is showing they completed (let's say) 10 tasks in (let's say) 16 days when they projected it would take 21 days to complete 10 tasks. (same as question 163)
I stand corrected. upon closer examination, I feel the project is [D. AT RISK]
The tracked data points thus far:
3 - days performing at the planned rate of features
4 - days performing above planned rate of features
9 - days performing below planned rate of features
THEREFORE: this Velocity Chart demonstrates a trend toward underperforming
This project is at risk
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TrebleSmith
1 month agoBlueMan93
1 month, 3 weeks agostinkle
2 months, 2 weeks ago044f354
4 months, 1 week ago044f354
4 months, 1 week ago044f354
4 months, 1 week agotduke
5 months ago