exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 204 discussion

Actual exam question from CompTIA's PK0-005
Question #: 204
Topic #: 1
[All PK0-005 Questions]

Which of the following can a project manager infer from the following velocity chart?

  • A. The project is on schedule.
  • B. The project is ahead of schedule.
  • C. The project is behind schedule.
  • D. The project is at risk.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
stinkle
4 weeks, 1 day ago
Selected Answer: B
Days of the month 1-29 and on the left, showing tasks remaining. I believe the project is ahead of schedule.
upvoted 1 times
...
044f354
2 months, 2 weeks ago
Selected Answer: D
I stand corrected. upon closer examination, I feel the project is [D. AT RISK] The tracked data points thus far: 3 - days performing at the planned rate of features 4 - days performing above planned rate of features 9 - days performing below planned rate of features THEREFORE: this Velocity Chart demonstrates a trend toward underperforming This project is at risk
upvoted 1 times
...
044f354
2 months, 2 weeks ago
Selected Answer: C
Y axis shows actual effort toward features is lagging slightly below planned timeline for features.
upvoted 1 times
044f354
2 months, 2 weeks ago
I'm wrong. this project is D. AT RISK
upvoted 1 times
...
...
tduke
3 months, 2 weeks ago
Selected Answer: C
Shows project is behind schedule.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago