During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?
Project baselines are the project’s starting point. They summarize the scope, cost,
and schedule that the project team and stakeholders agree upon. They are points
of reference for you as you track the project’s progress.
A WBS visually represents the project tasks in a hierarchical structure, outlining how the project will be broken down into manageable components. It includes information like tasks, durations, predecessors, and resource allocation, which aligns with the scenario described in the question.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
BrannyBran
2 weeks, 6 days agoBlueMan93
1 month agoZach123654
1 month, 1 week agoab00279
4 months ago