The Critical Chain Method
The critical chain method is a schedule network analysis method that allows you to consider
resource limitations and adjust the schedule as appropriate to work within those limitations. The
critical chain is established by analyzing the critical path alongside the resources that are actually
available. The critical chain method is also used to plan and manage reserves or buffers and helps
mitigate possible cost and schedule risks.
upvoted 1 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
leveragetech
Highly Voted 5 years, 1 month agosasquatchshrimp
Highly Voted 4 years, 3 months agoBraniac
Most Recent 2 years, 8 months agobrown705
2 years, 10 months agoAgr321
2 years, 7 months ago