Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

  • A. Critical Path Method
  • B. Critical Chain Method
  • C. Arrow Diagramming Method
  • D. Gantt Chart Method
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlvMicro
4 years, 4 months ago
An arrow diagram is defined as a process diagramming tool used to determine optimal sequence of events, and their interconnectivity. It is used for scheduling and to determine the critical path through nodes. The arrow diagramming method shows the required order of tasks in a project or process, the best schedule for the entire project, and potential scheduling and resource problems and their solutions. The arrow diagram lets you calculate the "critical path" of the project
upvoted 3 times
...
leveragetech
5 years, 4 months ago
C. Arrow Diagramming Method
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel