New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables.
Which of the following is the BEST way for the PM to validate the assessment?

  • A. Ask the team for estimates, and review the project schedule and budget.
  • B. Ask the team to review the product scope and validate its impact on the schedule and quality.
  • C. Ask the team for estimates, and review the cost management plan.
  • D. Ask the team to perform a SWOT analysis, and validate the assessment.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...