A recently added stakeholder is unaware of critical changes that will affect the department. Which of the following should the project manager do FIRST to ensure all parties have the same level of information?
A.
The project manager should check the project management plan to determine how the project should be managed and controlled.
B.
The project manager should check the communications plan to ensure stakeholders are included on any key messages.
C.
The project manager should check the meeting agenda to ensure the stakeholder is invited to all meetings.
D.
The project manager should ensure meeting minutes are distributed to all project members.
Currently there are no comments in this discussion, be the first to comment!
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.