A project manager is working on a large, complex project. While creating the project schedule, the project manager defines key points at which progress to date can be identified. Which of the following BEST describes the scheduling activity the project manager has completed?

  • A. Approval gate development
  • B. Milestone development
  • C. Critical path identification
  • D. Quality gate identification
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.