A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?
B should be the correct answer.
Based on CompTIA’s official exam objectives, the process should be:
1. Identify and document
2. Evaluate impact and justification
3. IDENTIFY APPROVAL AUTHORITY
4. Obtain approval
5. Implement change
6. Validate change/quality check
7. Update docs
8. Communicate throughout as needed
No, it's directly stated in the exam objectives. Furthermore, no CCB is mentioned in the question. Just a change request. From who? The customer? A team member? The answer really should be B: Identify approval authority.
It specifically states that the impact analysis is done.
It goes
1 - identify and document
2 - track requests
3 - evaluate the impact and justification
4 - disposition the request at the CCB
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Extrarice
Highly Voted 5 years agouser82
2 years, 5 months agoRz10
Highly Voted 4 years, 12 months agoIanBilbo12
4 years, 4 months agorose_y
Most Recent 3 years, 2 months agoKiddyb
3 years, 5 months agobzpunk
3 years, 9 months ago