A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the BEST chart to use?

  • A. Milestone
  • B. Gantt
  • C. Burndown
  • D. PERT
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Zach123654
2 days, 3 hours ago
Selected Answer: A
GPT: A
upvoted 1 times
...
stinkle
3 weeks, 1 day ago
Selected Answer: B
B. Gantt Chart A Gantt chart, while not called a "milestone chart," is commonly used to show both tasks and key milestones. Milestones are often displayed as markers on a Gantt chart to indicate major events or accomplishments. It’s a widely used project management tool for visualizing schedules and accomplishments. Conclusion: The term "Milestone Chart" isn’t a common specific term in the Project+ exam, but understanding how to track milestones using tools like Gantt charts or milestone lists is important
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago