Exam PK0-005 topic 1 question 170 discussion

Actual exam question from CompTIA's PK0-005
Question #: 170
Topic #: 1
[All PK0-005 Questions]

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Choose two.)

  • A. Purchase the materials.
  • B. Assign the resources.
  • C. Accept delays in the work.
  • D. Approve the deliverables.
  • E. Monitor the performance.
  • F. Negotiate with the vendors.
Show Suggested Answer Hide Answer
Suggested Answer: DE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
stinkle
1 month ago
Selected Answer: EF
You can't approve deliverables if they're not done yet.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.