Question #: 319
Topic #: 1
[All PK0-005 Questions]

Because milestones were not being met, a project manager decided to add more developers to the crucial tasks to help expedite the completion of deliverables. However, the developers’ performance did not improve. Which of the following team life cycles should the project manager move to next?

  • A. Forming
  • B. Norming
  • C. Storming
  • D. Adjourning
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
BlueMan93
2 weeks, 3 days ago
Selected Answer: C
Weird question, but if they are asking "what comes next after 'Forming'?" the next stage is Storming, then Norming.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...