Question #: 322
Topic #: 1
[All PK0-005 Questions]

A project manager is working with a new team to review a requirement for a new project. The project manager wants to create artifacts that include roles and responsibilities. Which of the following artifact types best matches these requirements?

  • A. RACI chart
  • B. Gantt chart
  • C. Burndown chart
  • D. Organizational chart
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
BlueMan93
1 month, 2 weeks ago
Selected Answer: A
RACI chart is best to determine who is responsible for what tasks.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...