A data scientist has constructed a model that meets the minimum performance requirements specified in the proposal for a prediction project. The data scientist thinks the model's accuracy should be improved, but the proposed deadline is approaching. Which of the following actions should the data scientist take first?

  • A. Continue collecting data.
  • B. Request additional funding.
  • C. Consult the key project stakeholder.
  • D. Test additional model specifications.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SuntzuLegacy
1 month, 1 week ago
Selected Answer: C
The first step is to communicate the trade-off between further improving the model and meeting the upcoming deadline to the person or group who defines project priorities. In other words, before investing more time, money, or effort, you need to ensure the key project stakeholder is aligned with any change in scope or timeline. Hence, the best first action is: C. Consult the key project stakeholder.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...