exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 321 discussion

Actual exam question from CompTIA's PK0-005
Question #: 321
Topic #: 1
[All PK0-005 Questions]

In a functional organizational structure, a project manager is trying to avoid a project roadblock due to a mobilization fee that has not been paid to a contractor. Which of the following should the project manager do?

  • A. Authorize payment from the contingency budget.
  • B. Follow up on the payment request with the payable clerk.
  • C. Negotiate with the contractor to be paid later in the project.
  • D. Escalate the issue to the financial controller.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Duke_CT
3 weeks, 3 days ago
Selected Answer: C
Its probably C, very likely
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...