exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 126 discussion

Actual exam question from CompTIA's PK0-004
Question #: 126
Topic #: 1
[All PK0-004 Questions]

A project manager has been assigned a complex project and does not know all the activities required to complete it.
Which of the following if the BEST approach to determine the work packages for the WBS?

  • A. Brainstorming
  • B. Analogous
  • C. Bottom-up
  • D. Forward pass
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
Highly Voted 4 years, 7 months ago
The answer is "A" -- Brainstorming
upvoted 6 times
...
Dansaki
Most Recent 2 years, 5 months ago
Selected Answer: C
C is correct. The question asks which is best? All are estimation techniques except maybe D. But the question is asking for the best and following the Comptia guide, Bottom up is the best and most accurate
upvoted 1 times
...
brown705
2 years, 10 months ago
Selected Answer: A
I think brainstorming is correct here.
upvoted 2 times
...
devildog
3 years, 1 month ago
I think the given answer may be correct: What is the bottom-up approach to a project? The bottom-up approach to project management means that you begin with brainstorming possible solutions to meet that final deliverable. In other words, you know what the project goal is, but are not sure (yet) how to get there.
upvoted 2 times
...
Born_Again
3 years, 1 month ago
Selected Answer: C
Therefore, the bottom-up estimates are the best, because we have moved from the initiation and business-case part of the project to the real scope of work, with real resources and schedule estimates. This allows the estimates to get as close as possible to reality at -5 percent to +10 percent. Many budgets fluctuate and bounce between those numbers during execution of project work. I would say that 10 percent is usually my tolerance level for being over/under budget. Anything over that tolerance lets me know that I need to take corrective action to fix the issues causing my budget to wildly fluctuate.
upvoted 1 times
...
Sabie
3 years, 6 months ago
Bottom up is used to determine budget and creating a WBS. This PM does not even know what the work entails so I would say the answer is brainstorming.
upvoted 2 times
...
asso217
3 years, 12 months ago
C. Bottom-up
upvoted 1 times
asso217
3 years, 11 months ago
Never mind, the correct answer is A. Brainstorming
upvoted 3 times
...
...
[Removed]
4 years, 7 months ago
If your organization typically undertakes projects that are similar in size, scope, and complexity, consider using your existing WBS as a template for future projects. It’s a great starting point for the new project and can help kick off the brainstorming session with the project team. (Comptia Project + Study guide 2nd ed.)
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago