A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance.
Which of the following should the PM do NEXT?

  • A. Crash the schedule.
  • B. Notify the project team.
  • C. Initiate a change request.
  • D. Accept the risk.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
abhnn
Highly Voted 4 years, 6 months ago
This should be C
upvoted 17 times
...
POWNED
Most Recent 2 years, 4 months ago
Selected Answer: C
Begin the change control process which would begin with justification. Answer is C
upvoted 1 times
...
MJVIS
2 years, 5 months ago
Do we know how these answers are selected or determined? For example: how is B the correct answer?
upvoted 1 times
...
ItsMeAgain99
2 years, 7 months ago
C. Always communicate the change first before implementing with project team.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago