Which of the following describes risk mitigation?

  • A. The transfer of the risk to another entity or project inside or outside the organization, along with associated costs.
  • B. The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.
  • C. The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.
  • D. The weighting or prioritization of the risk against all other identified risks within this project or others associated with it.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
4007
Highly Voted 3 years, 10 months ago
POE - I think Answer is B. The understanding of the risk with a detailed explanation of how the project intends to (mitigate or) address the potential for occurrence.
upvoted 7 times
Treymb6
3 years, 2 months ago
Sure, understanding the risk will help in the future with risk mitigation but that process itself isn't mitigating anything. The only answer here that is an actual mitigation action would be transferring, which would be A.
upvoted 2 times
hayo
2 years, 5 months ago
The question is not asking for a mitigation technique, but for the explanation of risk mitigation.
upvoted 1 times
...
...
...
Agr321
Most Recent 2 years, 7 months ago
Risk mitigation Attempts to reduce the probability or impact of a potential risk event to an acceptable level. Mitigation may involve implementing a new course of action in an effort to reduce the problem or changing the current conditions so that the probability of the risk occurring is reduced. Sometimes, when reducing the probability is not possible, the focus must be on reducing the consequences of the risk event.
upvoted 1 times
...
some_specialist
2 years, 10 months ago
Selected Answer: A
My reasoning why A is the correct answer, is because B is more like Risk Acceptance than Risk Mitigation.
upvoted 1 times
...
harinezumi
4 years, 4 months ago
Risk mitigation is a risk strategy for negative risks whereby the project team reduces the probability that the risk will occur or lessens the projected impact of the risk. Pearson, 2018
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago