Exam PK0-004 topic 1 question 120 discussion

Actual exam question from CompTIA's PK0-004
Question #: 120
Topic #: 1
[All PK0-004 Questions]

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?

  • A. Issue log and process diagram
  • B. Resource analysis and Gantt chart
  • C. Stakeholder analysis and communication plan
  • D. Scatter chart and scope analysis
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sasquatchshrimp
Highly Voted 4 years, 3 months ago
Would it not be C? The department manager does not know the status, so I am thinking the small project team skipped out on the communication plan to the stakeholders. Thoughts?
upvoted 13 times
thorstedc
4 years, 2 months ago
a Gantt chart would give the schedule for how long the resources from the department are needed and the resource analysis will show contrast to using the employees for the project and not using them in the department.
upvoted 4 times
...
...
hayo
Most Recent 2 years, 5 months ago
Selected Answer: B
B. Resource analysis and Gantt chart The manager does not think that the available resources (people) are not being used effectively. Also the Gantt chart will give the schedule
upvoted 2 times
...
boooliyooo
3 years, 1 month ago
In a Gantt chart, the project manager, team members, and stakeholders can see the following schedule characteristics: - pg 256 CompTIA Project+ Cert Guide
upvoted 1 times
...
Doscar
3 years, 5 months ago
for me it´s C, the department manager doesn't know about the status of the project, and the sentence never said that having a few people working on the project is a problem, just said that the manager doesn't know the progress
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago