A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?
Would it not be C? The department manager does not know the status, so I am thinking the small project team skipped out on the communication plan to the stakeholders. Thoughts?
a Gantt chart would give the schedule for how long the resources from the department are needed and the resource analysis will show contrast to using the employees for the project and not using them in the department.
B. Resource analysis and Gantt chart
The manager does not think that the available resources (people) are not being used effectively. Also the Gantt chart will give the schedule
In a Gantt chart, the
project manager, team members, and stakeholders can see the following schedule
characteristics: - pg 256 CompTIA Project+ Cert Guide
for me it´s C, the department manager doesn't know about the status of the project, and the sentence never said that having a few people working on the project is a problem, just said that the manager doesn't know the progress
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sasquatchshrimp
Highly Voted 4 years, 3 months agothorstedc
4 years, 2 months agohayo
Most Recent 2 years, 5 months agoboooliyooo
3 years, 1 month agoDoscar
3 years, 5 months ago