Below are the steps for creating a schedule according to certify:
1. Determine Tasks
2. Sequence Tasks
3. Allocate resources
4. Determine task duration including start and end dates.
5. Determine milestones
6. Construct the schedule
7. Determine the critical path
8. Set the baseline and obtain approval
9. Set quality gates
10. Establish the governance process
The given answer is correct according to 1.6. You need to assign tasks the members now
upvoted 3 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
l0609890
Highly Voted 4 years agoT_rowe
Most Recent 4 years, 2 months agoexamdominator
4 years ago