A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

  • A. durations.
  • B. tasks.
  • C. critical path.
  • D. resources.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
l0609890
Highly Voted 4 years ago
Yup examdominator is right! Below are the steps for creating a schedule according to certify: 1. Determine Tasks 2. Sequence Tasks 3. Allocate resources 4. Determine task duration including start and end dates. 5. Determine milestones 6. Construct the schedule 7. Determine the critical path 8. Set the baseline and obtain approval 9. Set quality gates 10. Establish the governance process
upvoted 10 times
...
T_rowe
Most Recent 4 years, 2 months ago
if they finished the WBS then they already know the tasks.
upvoted 3 times
examdominator
4 years ago
The given answer is correct according to 1.6. You need to assign tasks the members now
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago