exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 183 discussion

Actual exam question from CompTIA's PK0-004
Question #: 183
Topic #: 1
[All PK0-004 Questions]

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.
This type of analysis is an example of which of the following?

  • A. Cost performance index
  • B. Risk mitigation
  • C. Schedule variance
  • D. Cost variance
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hayo
2 years, 5 months ago
Schedule variance is represented in a dollar figure. https://project-management.com/schedule-variance-formula/ There is not enough info in this question to distinguish between cost or schedule variance.
upvoted 1 times
...
Braniac
2 years, 8 months ago
Schedule variance is an indicator of whether a project schedule is ahead or behind.... Can't very well represent that "in a dollar figure." Its cost variance don't get tripped up on terminology.
upvoted 1 times
Noralie
2 years, 7 months ago
Schedule variance is only represented in dollar figure $1000 ahead of schedule $0 in schedule -$1000 behind schedule https://www.wrike.com/project-management-guide/faq/what-is-schedule-variance-in-project-management/
upvoted 1 times
...
...
JohnWH
3 years, 9 months ago
@I0609890 is 100% correct. answer is schedule variance.
upvoted 2 times
...
Codly
3 years, 11 months ago
How is this C?
upvoted 1 times
...
examdominator
4 years, 1 month ago
cost variance.
upvoted 2 times
l0609890
4 years ago
No, it is still schedule variance. SV = EV - PV CV = EV - AC
upvoted 6 times
BungALung
4 years ago
It is Cost Variance.
upvoted 1 times
izz123
3 years, 10 months ago
Schedule Variance = Earned Value - Planned Value. The answer is schedule variance. Nowhere in the question does it say anything about Actual Cost.
upvoted 4 times
Wes_60
3 years, 7 months ago
I I captain.
upvoted 1 times
...
...
...
dyers
3 years, 9 months ago
I was surprised to learn schedule variance is actually measured in dollars. This question is definitely intended to throw you off track by providing two "cost" answers.
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago