Actual exam question from CompTIA's PK0-004
Question #: 132
Topic #: 1
[All PK0-004 Questions]

Which of the following shows projected project expenditures?

  • A. Work breakdown structure
  • B. Cash flow schedule
  • C. Cash burn rate
  • D. Budget milestone
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
HCEYLAN
2 years, 5 months ago
Selected Answer: C
I selected Answer C
upvoted 1 times
...
Jo1988
3 years, 2 months ago
I think WBS is correct. This website explicitly states that https://www.workbreakdownstructure.com/
upvoted 1 times
...
HelloMyNameIs
4 years ago
Answer A is the correct answer, taken from Sybex Project+ Study Guide, 2nd Edition, page 80. "A WBS is one of the fundamental building blocks of project planning. It will be used as an input to numerous other planning processes. It's also the basis for estimating activity duration, assigning resources to activities, estimating work effort, and creating a budget." Cash burn rate would be a good answer but burn rate is measuring the project expenditures to-date rather than projected project expenditures. As for Cash Flow, I couldn't find much information on Google regarding that as it relates to Project Management and the only related definitions, at least in title, are cash flow techniques and not cash flow schedules, which includes Discounted Cash Flow, Net Present Value, and Internal Rate of Return which are more economic models predicting revenue.
upvoted 4 times
...
l0609890
4 years, 1 month ago
I feel the answer should be a cash flow schedule because it shows the estimated and schedules cash disbursement of the project by time period. WBS doesn't show the projected project expenditures but rather the work that has to be done to successfully produce a deliverable. I think it is confusing it with the Cost Breakdown Structure.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago