exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 282 discussion

Actual exam question from CompTIA's PK0-004
Question #: 282
Topic #: 1
[All PK0-004 Questions]

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.
The constraint described in this scenario is:

  • A. cost
  • B. environmental
  • C. scope
  • D. scheduling
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
asso217
Highly Voted 3 years, 12 months ago
No matter how close you are to managing a project, there are certain factors even the most experienced project managers simply cannot control. Competition for resources, scope creep, and changing risks are three constant headaches for project managers that can lead to shifting strategic priorities. The scope is the correct answer.
upvoted 5 times
...
cmarcos97
Most Recent 4 years ago
Can someone confirm? I feel like it should be cost.
upvoted 2 times
hayo
2 years, 5 months ago
The company is changing its strategic goals, and the project's scope no longer aligns with these new goals. There is no mention of cost being the reason the project is being canceled.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago