If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

  • A. The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
  • B. The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
  • C. The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
  • D. The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
4007
Highly Voted 3 years, 10 months ago
B. The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report. According to the PMBOK, the schedule baseline is the approved version of the schedule model that is used as a basis for comparison to the actual results. I think "compare" would be a better word choice than "apply" here (because the schedule baseline does not change) but answer B seems to be correct.
upvoted 7 times
...
SamWiseGam
Most Recent 2 years, 5 months ago
I would be very surprised to see this question on an actual CompTIA exam. 2 of them state presenting it to the PM, but the PM is the one gathering the info. Project Champions don't exist. B
upvoted 1 times
hayo
2 years, 5 months ago
The champion is just another name for sponsor. They are interchangeable.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.