exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 10 discussion

Actual exam question from CompTIA's PK0-004
Question #: 10
Topic #: 1
[All PK0-004 Questions]

There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks -

A, B, F: 8 weeks -

D, E, H: 12 weeks -

D, B, F: 7 weeks -
Which of the following tasks are on the critical path?

  • A. A, C, G
  • B. A, B, F
  • C. D, E, H
  • D. D, B, F
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
cepojo
2 years, 3 months ago
Selected Answer: C
Correct "Critical Path" is the path of tasks that depend on each other and take the longest amount of time. It is critical because if any tasks in that dependency chain are delayed the entire project is delayed, thus critical path.
upvoted 1 times
...
Jakesn
3 years, 8 months ago
Answer is C. 12 weeks .Longest path is correct answer using Critical Path method.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago