Correct
"Critical Path" is the path of tasks that depend on each other and take the longest amount of time. It is critical because if any tasks in that dependency chain are delayed the entire project is delayed, thus critical path.
Answer is C. 12 weeks .Longest path is correct answer using Critical Path method.
upvoted 3 times
...