A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint.
Which of the following should the Scrum master do to improve the team's velocity in the next sprint?

  • A. Take a more hands-on leadership approach.
  • B. Add the unfinished work to the backlog.
  • C. Schedule a sprint retrospective.
  • D. Hold additional daily stand-up meetings.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 5 months ago
Selected Answer: C
What went well (keep doing these things) What could be improved (went OK, but could be better) What went badly (don't do these things again) Focus for next period/sprint/month/quarter (One or two things to focus on)
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
C. sprint retrospective
upvoted 2 times
...
Manzer
2 years, 7 months ago
Selected Answer: C
The sprint retrospective is a recurring meeting held at the end of a sprint used to discuss what went well during the previous sprint cycle and what can be improved for the next sprint. The Agile sprint retrospective is an essential part of the Scrum framework for developing, delivering, and managing complex projects.
upvoted 3 times
...
[Removed]
2 years, 10 months ago
The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago