A major project task involves purchasing and implementing computer equipment with special software, which is valued at $1.5 million, for a 700-employee organization. An IT department manager challenged the PM's ability to authorize expenditures after the purchase was made.
Which of the following documents should the PM provide to the functional manager?

  • A. Organizational chart
  • B. Project charter
  • C. Cost management plan
  • D. Change management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
project_tester
Highly Voted 3 years, 7 months ago
B. Project charter...
upvoted 10 times
...
MJVIS
Most Recent 2 years, 5 months ago
Selected Answer: B
I am going with Project Charter. I don't understand why the answer is -organizational chart. How are these answers decided?
upvoted 1 times
...
[Removed]
2 years, 10 months ago
Selected Answer: B
An Org Chart will show who reports to who. Project Charter refers to a statement of objectives in a project. This statement also sets out detailed project goals, roles and responsibilities, identifies the main stakeholders, and the level of authority of a project manager.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago