exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 353 discussion

Actual exam question from CompTIA's PK0-004
Question #: 353
Topic #: 1
[All PK0-004 Questions]

The following tasks are required to complete an IT project that is behind schedule:

Which of the following is the critical path?

  • A. 3, 2, 4
  • B. 4, 2, 3
  • C. 3, 2, 1, 4
  • D. 4, 1, 2, 3
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
project_tester
Highly Voted 3 years, 7 months ago
Shouldn't this be A?
upvoted 6 times
...
POWNED
Most Recent 2 years, 4 months ago
Selected Answer: B
The answer is B. Successor means it comes before the task. This makes 4 the first task 1 and 2 the second, but 2 has a longer duration. Task 3 is dependent on 1 and 2. The critical path is 4,2,3
upvoted 2 times
...
Ony
3 years, 6 months ago
What?! We are talking the critical path (longest path) and successors (task that follows). With that said it makes sense 4 comes first (no dependencies), then 2 (because it is the longest duration), then 3.
upvoted 1 times
Ony
3 years, 6 months ago
Bah nvm, successor vs predecessor. A is correct....
upvoted 4 times
...
...
Wes_60
3 years, 7 months ago
This should be A.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago