The answer is B. Successor means it comes before the task. This makes 4 the first task 1 and 2 the second, but 2 has a longer duration. Task 3 is dependent on 1 and 2. The critical path is 4,2,3
What?! We are talking the critical path (longest path) and successors (task that follows). With that said it makes sense 4 comes first (no dependencies), then 2 (because it is the longest duration), then 3.
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
project_tester
Highly Voted 3 years, 7 months agoPOWNED
Most Recent 2 years, 4 months agoOny
3 years, 6 months agoOny
3 years, 6 months agoWes_60
3 years, 7 months ago