A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date.
If more resources are provided, which of the following strategies would BEST help to achieve the new date?

  • A. Fast track
  • B. Burn
  • C. Crash
  • D. Reduce durations
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Birch02
Highly Voted 3 years, 7 months ago
C. Crash
upvoted 11 times
...
[Removed]
Highly Voted 3 years, 6 months ago
CRASH!!!!
upvoted 5 times
...
MJVIS
Most Recent 2 years, 5 months ago
Selected Answer: C
Crash is a method in project management that helps you speed up the timeline of a project through the addition of resources.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: C
C. Crashing
upvoted 1 times
...
[Removed]
2 years, 10 months ago
Selected Answer: C
fast track is moving the task schedule so the tasks run in parallel to compress the schedule. Crashing is when you add additional resources to get the work done faster.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago