Exam PK0-004 topic 1 question 516 discussion

Actual exam question from CompTIA's PK0-004
Question #: 516
Topic #: 1
[All PK0-004 Questions]

A functional manager within a project is requesting to edit the display features of an application that is being developed.
Which of the following has the authority to approve the edit?

  • A. PM
  • B. CCB
  • C. PMO
  • D. SME
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Bimbim555
Highly Voted 3 years, 6 months ago
Can someone explain why the answer is PM, why not CCB?
upvoted 8 times
wisut
2 years, 10 months ago
Should be CCB
upvoted 2 times
...
...
kmanb
Most Recent 2 years, 3 months ago
Selected Answer: B
The change control board (CCB) has the authority to approve the edit requested by the functional manager. The change control board (CCB) is a group of individuals responsible for reviewing and approving changes to the project, including changes to scope, schedule, budget, and quality. The CCB typically includes representatives from various stakeholders, including the project manager, functional managers, and subject matter experts (SMEs). In this case, the functional manager within the project is requesting to edit the display features of an application that is being developed, which would likely be considered a change to the project. As such, the CCB would have the authority to review and approve the edit requested by the functional manager. While the project manager (PM) and the project management office (PMO) may also be involved in the process, they would typically not have the final say on whether the change is approved or not. Instead, it would be up to the CCB to make the final decision on whether to approve the edit.
upvoted 1 times
...
[Removed]
2 years, 10 months ago
requesting to edit the display features of an application This would simply fall under the change control procedure. editing the display could impact the project and the change would need to be approved, validated and communicated. the PM would not and could not make that determination.
upvoted 2 times
...
spoiledsalsa
2 years, 10 months ago
CCB isn't used for small items like display features... and in this scenario, we're approving an "edit." All other options are overkill or irrelevant. This fall under the realm of integrated change control, which is the responsibility of the PM. Verbal changes that happen in the project be should be documented.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago