Risk ID 2 has occurred.

Which of the following ways should the project manager update the risk register?

  • A. Add a column for probability and set risk 2 at 100%
  • B. Change the risk 2 response to backups restored
  • C. Change the risk 2 status to issue
  • D. Change the risk 2 owner to PM
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
POWNED
2 years, 4 months ago
Selected Answer: C
C change status to issue
upvoted 2 times
...
ItsMeAgain99
2 years, 7 months ago
B. is possible since risk register includes a plan of corrective action to the risk.
upvoted 1 times
...
chernukha101
3 years, 6 months ago
Should change the status to issue
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago