Exam PK0-004 topic 1 question 594 discussion

Actual exam question from CompTIA's PK0-004
Question #: 594
Topic #: 1
[All PK0-004 Questions]

A first-time project manager is developing a project charter.
Which of the following are key elements to have the project charter approved? (Choose two.)

  • A. Project team
  • B. Business case
  • C. Detailed risks
  • D. Requirements
  • E. Service-level agreement
  • F. Detailed budget
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
blah111
Highly Voted 3 years, 6 months ago
I think it's B and D
upvoted 11 times
...
MJVIS
Most Recent 2 years, 5 months ago
A Business Case and High-level Requirements are included in the project charter.
upvoted 1 times
...
MJVIS
2 years, 5 months ago
What is going on with the answers? How are these answers determined? The project team or resources are selected during the planning phase. A Business Case or High-level Requirements are included in the project charter.
upvoted 1 times
...
ExamTopics274
2 years, 5 months ago
Selected Answer: BD
This is B & D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago