A testing event was held and deemed unsuccessful. After review, it becomes clear that the two project teams had different expectations of the testing. Which of the following is needed between the two teams?
A. Communication plan
If the two project teams had different expectations of the testing event, it suggests that there may have been a lack of effective communication between the teams. A communication plan can help to ensure that all team members have a clear understanding of the project goals and objectives, and can help to prevent misunderstandings or miscommunications. A communication plan should outline how information will be shared between the teams, who is responsible for communicating what, and how often communication will take place. It can also include guidelines for how team members should communicate with each other and with stakeholders, and can help to ensure that everyone is on the same page.
I think the given answer of A is correct. If there was proper communication between the teams, then we wouldn't have that issue.
upvoted 5 times
...
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
kmanb
2 years, 3 months agoManzer
2 years, 7 months agoJon0369
3 years, 4 months agoKiddyb
3 years, 4 months ago