Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?

  • A. Supply Ann with the requested tablet.
  • B. Have Ann submit a change request.
  • C. Provide Ann with a copy of the project management plan.
  • D. Inform Ann that she will receive what has been authorized.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Bimbim555
Highly Voted 3 years, 4 months ago
Selected Answer: B
This should be B
upvoted 6 times
...
moses23
Highly Voted 3 years, 4 months ago
Selected Answer: B
bbbbbb
upvoted 6 times
...
MJVIS
Most Recent 2 years, 5 months ago
Selected Answer: B
The requirement for a laptop has changed to a tablet. Therefore, Ann has to submit a change request.
upvoted 1 times
...
brvndvnwolf
2 years, 5 months ago
Selected Answer: B
B. Submit change request
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago